So progress is going well but SLOW
![😂](//twemoji.maxcdn.com/2/svg/1f602.svg)
Hopefully I'm heading in the right direction...
I've started building a 2" CCVM
* 50 litre stainless keg
* 2" hole for filling
* no drain hole yet.. Need an idea
* 1.3m column
* 2" 600mm X4 (15mm pipes) shotgun condenser
* 3000kw electric heater (with controller)
* 9mm copper reflux coil (single wound with finger)
* 6mm cooling pipes (ran from mains supply)
* fine welding wire and copper scrubbies packing (1.3m)
* sight glass
Few questions:
1) looking at the photos, does my T piece need a copper extension for the RC to slide in or is the height OK as it is?
2) out of the PC can I drop down to 15mm pipe? Will this also work in pot still mode, or do you need more pressure relief?
3) I haven't drilled a drain hole yet... 2" ferrule drain valves are very expensive. Could I possibly solder a piece of 22mm pipe directly into a hole in the keg, or is there a simple bulk head fitting? Access inside the keg is limited as I only have x2 2" access ports on the top, and a 2.5" hole for the heater ferrule.
Thanks!!