FractionalDisMan wrote:I need a 53kw electric still control. The spec below. Something like http://distillerycontrols.com/integrate ... ol-center/" onclick="window.open(this.href);return false;" rel="nofollow. I tried to get http://distillerycontrols.com/" onclick="window.open(this.href);return false;" rel="nofollow to quote but I think they are out of business. I emailed 3 times and got no reply. Any one have another company that does this sort of thing?
Power in:
2 each
70A 3 phase Y (208v)
(140A total. Must be wired split into two 70A)
Heaters:
12 each
4400w, 240v
I will hard wire, no plugs
Pot Control:
Timmed/delayed start (for preheating mash)
PID temp control, RTD input
Manual power control
High alarm
Mixer Motor:
1 each
5 HP, 3 phase
Speed control (simple VFD)
Will hard wire to motor, no plugs
On/Off
Wash Pump:
1 each
3 HP, 3 phase
Will hard wire, no plugs
On/Of Control
Dephlegmator Control
1 each 24vdc solenoid valve, NO
1 each 24vdc solenoid valve, NC
Control:
Both solenoids are on for cooling
PID temp control, RTD input
Other:
2 each temperature readouts, no control, high alarm, RTD input
1 programmable timer with alarm
GFI protection on heaters
Circuit overload protection on heaters
Circuit overload protection on motors
Electrical cabinets (gray, steel)
Need 54kw control system
Moderator: Site Moderator
-
- Novice
- Posts: 31
- Joined: Mon Sep 27, 2010 3:42 pm
Need 54kw control system
Please see viewtopic.php?f=85&t=70225
- Single Malt Yinzer
- Trainee
- Posts: 974
- Joined: Fri Sep 23, 2016 3:20 pm
Re: Need 54kw control system
http://stilldragon.com/" onclick="window.open(this.href);return false;" rel="nofollow
http://distillery-equipment.com/" onclick="window.open(this.href);return false;" rel="nofollow
Either one should be able to provide what you need or something close.
http://distillery-equipment.com/" onclick="window.open(this.href);return false;" rel="nofollow
Either one should be able to provide what you need or something close.
-
- Swill Maker
- Posts: 314
- Joined: Thu Jun 01, 2017 3:38 pm
- Location: New Zealand
Re: Need 54kw control system
53kw is 53,000 Watts
Do you mean 5300 Watts, aka 5.3kw?
Do you mean 5300 Watts, aka 5.3kw?
- Danespirit
- Master of Distillation
- Posts: 2648
- Joined: Tue Dec 25, 2012 8:09 am
- Location: Denmark
Re: Need 54kw control system
hpby98 Nope, I think he means what he writes 12 elements at 4400 W each is just shy of 53 KW.
He's posting in the section for craft distillers, this won't be a hobby scale rig.
He's posting in the section for craft distillers, this won't be a hobby scale rig.
- Bushman
- Admin
- Posts: 18337
- Joined: Tue Mar 30, 2010 5:29 am
- Location: Pacific Northwest
Re: Need 54kw control system
I've never dealt with Swede but he has been around for a long time making controllers. Not positive but I think he lives in Canada.
- cede
- Swill Maker
- Posts: 363
- Joined: Wed Jan 12, 2011 6:39 am
- Location: Canada
Re: Need 54kw control system
Yep Swede is in Canada.
-
- Distiller
- Posts: 2444
- Joined: Sun Oct 16, 2016 3:29 pm
- Location: At the edge of the Wild Wood
Re: Need 54kw control system
WTF - This BS is way outside "hobby" level - and all these cross references cast a little more suspicion !
- shadylane
- Master of Distillation
- Posts: 11484
- Joined: Sat Oct 27, 2007 11:54 pm
- Location: Hiding In the Boiler room of the Insane asylum
Re: Need 54kw control system
Don't get your panty's in a bind. This is the "Craft Distillers" section 

- HDNB
- Site Mod
- Posts: 7427
- Joined: Mon Feb 17, 2014 10:04 am
- Location: the f-f-fu frozen north
Re: Need 54kw control system
a bit big for hobby. we'll consider this asked and answered with a lock instead of delete.
Post your credentials in sig line with link to your distillery and i'll open it again in craft distillers topic.
Post your credentials in sig line with link to your distillery and i'll open it again in craft distillers topic.
I finally quit drinking for good.
now i drink for evil.
now i drink for evil.
- HDNB
- Site Mod
- Posts: 7427
- Joined: Mon Feb 17, 2014 10:04 am
- Location: the f-f-fu frozen north
Re: Need 54kw control system
i'm reopening in craft distilling after discussion with the OP. I think there are people here that can and will help with the source of the equipment required for the goal.
electric equipment is not a problem from my perspective.
It is a craft distillery we are talking about and OP is the installing contractor, not the owner, so he is not at liberty to post the name and DSP.
electric equipment is not a problem from my perspective.
It is a craft distillery we are talking about and OP is the installing contractor, not the owner, so he is not at liberty to post the name and DSP.
I finally quit drinking for good.
now i drink for evil.
now i drink for evil.
- Saltbush Bill
- Site Mod
- Posts: 10528
- Joined: Thu Mar 17, 2011 2:13 am
- Location: Northern NSW Australia
Re: Need 54kw control system
Swede would be the bloke to see. Id try and contact him again, doubt hes gone out of business.
-
- Novice
- Posts: 31
- Joined: Mon Sep 27, 2010 3:42 pm
Re: Need 54kw control system
Well I could never get any reply to inquires to build the system. I ended up building myself. Got all parts from Automation Direct. Control is a Productivity 2k PLC. System working good. Needs some fine tuning on the automatic controls and recipes. I wired the heaters into 4 banks of three heaters connected in a delta configuration. I put a third SSR on each bank for safety. Each bank is burst fire time base control. I delayed the turn on time of each bank 1/4 of the time base. This way the heaters turn on is staggered so the heaters do not turn on and off all at the same time. Two Industrial GFIs monitor the heaters for current leakage. Mixer speed control is a VFD also from AD. Wash motor and mixer protected w/ overload breakers. Delay auto start, Run until, etc all programed in. Display he went with the 15" touch screen. Down the road will add logging and remote monitor and control w/ phone. The unit is installed in a licensed system in California. No names until the doors open.
- cede
- Swill Maker
- Posts: 363
- Joined: Wed Jan 12, 2011 6:39 am
- Location: Canada
Re: Need 54kw control system
Nice Job ! 